Open: Works Orders > Processing > Enter Costs > Operation Times/Costs.
If the operation is not on the list (it is an addition to the estimated operations) or if the works order is a batch order (the works order was not created from an estimate), you will need to enter a Reference and Description manually.
Once created, operations are permanently stored against works orders.
If appropriate, enter the quantity now completed.
If this is not a batch works order, leave the quantity as 0 (zero), or enter 1 as appropriate.
Enter the Labour, Machine, Setup and Subcontract cost times.
Manufacturing has a unique entry system for entering times. You can enter time in any of the following formats:
Entering 65 displays 65h 0m (65 hours zero minutes).
Entering 6{space}5 displays 6h 5m (6 hours 5 minutes).
Entering 6h5m displays 6h 5m (6 hours 5 minutes).
Entering 65m displays 1h 5m (1 hour 5 minutes).
Click in the Costs box from the Enter Operation Times/Costs or Enter Timesheets windows to enter operation costs.
The costs so far recorded against the operation are displayed, broken down over the various cost headings.